GeMech drilling project for piling

Contiguous Piles – Wolverhampton

A great image from our foreman Rob Wright on site in Wolverhampton, where we’re installing 15.0m deep 350mm diameter contiguous pile walls in to Mudstone for repeat client Speller Metcalfe, to form a perimeter wall around a pre-existing mine shaft which has been grouted prior to commencement. Once these operations have been completed, we will be returning to site at a later date to provide a ground improvement solution using vibro-stone columns.